In order to obtain authorisation to work near the tramway you must submit a Metrolink Work Request Form, saying where and when you want to work, and describing the work to be done.

Alternatively you can download a PDF copy of the form here. Please complete and post to:

Civil Engineer
Metrolink House
Queens Road
Manchester
N8 0RY
Tel: 0161 205 8665
Fax: 0161 205 1095

Completed Work Request Forms must be returned to us at least three weeks before you intend to start work. Major works may need more notice. If you have prepared a method statement, you should send it with your Work Request Form. If the work needs to be submitted to the Highway Authority under the New Roads and Street Works Act, the same information will usually be suitable for Metrolink. Please submit this to Metrolink with your Work Request Form.

* denotes a required field

Who you are and where you are working

This is for SPAM protection, please leave blank to complete submission

* Site Description:

* Name:

* Contact Number:

* Address:

Please detail the steps in the work for example: Erect scaffold; carry out roof inspection; dismantle scaffold. We may need to issue permits for each stage and/or isolate the over head wire.

* 1

2

3

4

5

6

7

8

9

When a 'Metrolink' permit is required

A Metrolink permit will be required if you answer 'yes' to any of the following questions:

* Could any part of the work zone, plant, tools suspended load or persons encroah within the Metrolink Hazard Zone?

Yes

No

* Will pedestrians be diverted to within the Metrolink Hazard Zone?

Yes

No

* Does the work include any of the following within 4 metres of the Metrolink Hazard Zone? Piling, using a crane, excavation over 2 metres deep or erecting / dismantling scaffold

Yes

No

* Does the work involve any excavation within 3 metres of any pole supporting overhead wires?

Yes

No

* Does any part of the access route to the work site (for persons or plant) encroach within the Metrolink Hazard Zone?

Yes

No

* Could any part of the works affect the Metrolink infrastructure or operation of the Metrolink scheme?

Yes

No

When a 'Metrolink' isolation is required

A Metrolink isolation may be required if you answer yes to any of the following questions:

* Is there a risk that any part of the operation will encroach within 3 metres of the OHLE wire?

Yes

No

* Is there a risk that rail continuity or any bonding cables will be broken?

Yes

No

* Is plant to be used beneath the OHLE wires?

Yes

No